SEWAGE TREATMENT PLANTS

Sand Filter in Wastewater Treatment

Case study overview

Date

March 2022

Location

Listowel, Co. Kerry

Industry Sector

Residential

Product Used

Sandcel Sand polishing filter and Sewage Treatment plant (Novo UK6)

Project Introduction

The purpose of this case study is to highlight the challenges and installation of a sand filter in wastewater treatment. This project involves the extension and renovation of an existing dwelling in Listowel, a heritage market town in County Kerry. The site assessor was also the contractor for this wastewater installation.

Request a quote for your project today!

THE CHALLENGE

Considering the poor ground conditions and the lack of space, Denis O’Connell (Civil Engineering) recommended the ideal solution that would work in the area – A Tricel Novo wastewater treatment plant with a Sandcel Sand polishing filter.

The Installation

Below are images showing the steps involved in installing the Sandcel Sand Polishing Filter. The sand filter is a tertiary treatment consisting of stratified layers of certified sands in accordance with the EPA Code of Practice.

Sandcel step 1
Sandcel step 2
Sandcel step 3
Sandcel step 4
Sandcel step 5

GRP panels are installed with gravel distribution layers and distribution pipes as a base layer. Effluent is distributed evenly across the entire surface area of the filter media by the pipework within the top pea-gravel layer – the capping is made with gravel.

Afterwards, a geotextile is placed on top. Geotextile is rot-proof, irremovable, and permeable, making it ideal for separating materials that cannot mix while still allowing water to drain.

Sandcel installation process
Sandcel step 8
Sandcel step 7

If you are looking for a solution to upgrade your septic tank  for small communities, businesses, schools, leisure centres or hotels, please don’t hesitate to get in touch with us today to discuss your requirements and find a suitable solution.

IF YOU NEED MORE INFORMATION

Call us now to talk about your project and we will answer your questions or concerns.

ASK FOR A QUOTE

Request a free quote today to have a quote that meets your project!

Other case studies you might like

Wastewater treatment project

The wastewater treatment project was to upgrade an existing and obsolete system. (2022)


2 min 30

Septic tank wet ground upgrade

Tricel provides Tricel Novo wastewater treatment plant with a Sandcel sand polishing filter to upgrade an old existing septic tank in a wet area. (2022)
2 min

Septic tank upgrade into a Novo

Tricel provides Tricel Novo wastewater treatment plant with a Sandcel sand polishing filter to upgrade the existing septic tank.

2 min 30

Commercial Wastewater Treatment Systems

Upgrade to an existing wastewater treatment system in a cheese processing factory (2022)
3 min

Sewage treatment plant for hotels

The client needed wastewater treatment for hotels to increase effluent performance. (2022)

3 min

Commercial wastewater denmark

A commercial wastewater system is installed at a camping site with a capacity for 130 caravans. (2015)
3 min 30

Septic tank upgrade

Tricel provides Novo wastewater treatment plant with a Sandcel sand polishing filter as a solution for a septic tank upgrade. (2016)
2 min 30

sand filter in wastewater treatment

Extension and refurbishment to an existing dwelling with Sandcel Sand polishing filter and Sewage Treatment plant (Novo UK6).

2 min 30

See all case studies


Source through all of our successful projects


2 min 30

Get in touch

 

Error: Contact form not found.